Paved Driveway
In this project I was asked to stone pave a driveway:
1. On the first day the whole drive was cleared and concrete laid
2. When dry, I then laid the stones onto a sand/cement base
3. Finished off by pointing all the stones
1. On the first day the whole drive was cleared and concrete laid
2. When dry, I then laid the stones onto a sand/cement base
3. Finished off by pointing all the stones
Friday, 9 November 2012
Block Tiled Floor
In this project I had to create a floor using old style block tiles in a herringbone pattern:
1. All the rubble was cleared and the area levelled
2. I put down a membrane before laying a concrete base
3. When dry, I began laying the block tiles onto a sand base (as shown in photo)
4. After all the blocks were laid and grouted I applied 2 coats of sealant oil
2. I put down a membrane before laying a concrete base
3. When dry, I began laying the block tiles onto a sand base (as shown in photo)
4. After all the blocks were laid and grouted I applied 2 coats of sealant oil